NOTE: You have to reload this page before the materials sheet will update, hit F5.
| Category | Units | Amount | Cost To Buy | List | Total Purchased, Units | Total Purchased, Dollar Amount | |
|---|---|---|---|---|---|---|---|
| Fabric | SQFT | 525.00 | $ 38.07 | Fabric(350.00), Fabric(175.00), | 0 | 0 | See Invoice List-> |
| 1-1/2" Rock | TONS | 10.00 | $ 540.00 | 1-1/2" Local River Rock(5.00), 1-1/2" Local River Rock(3.50), 1-1/2" Local River Rock(1.50), | 0 | 0 | See Invoice List-> |
| Wall | TONS | 4.00 | $ 192.00 | Wall Blocks(4.00), | 0 | 0 | See Invoice List-> |
| Cap | TONS | 5.00 | $ 42.50 | Caps(5.00), | 0 | 0 | See Invoice List-> |
| Demo | SQFT | 1025.00 | $ 750.00 | Demo Rock(275.00), Demo Sod(750.00), | 0 | 0 | See Invoice List-> |
| Concrete | 146.00 | $ 2485.00 | Concrete,Grey Broom(145.00), Concrete,Boom Pump(1.00), | 0 | 0 | See Invoice List-> | |
| Miscellaneous | 2.00 | $ 1200.00 | Miscellaneous(1.00), Miscellaneous(1.00), | 0 | 0 | See Invoice List-> | |
| 5"-12" Rock | Ton | 2.00 | $ 810.30 | 5"-12" Horizon Cobble(1.00), 5"-12" Horizon Cobble(1.00), | 0 | 0 | See Invoice List-> |
| Item Description | Amount Needed | Total Purchased, Units | Total Purchased, Dollar Amount | |
|---|---|---|---|---|
Oger and Parts |
1.00 | 0 | 0 | See Invoice List-> |
Oger and Parts |
1.00 | 0 | 0 | See Invoice List-> |
| Fabric | 1-1/2" Rock | Wall | Cap | Demo | Concrete | Miscellaneous | MOB | 5"-12" Rock | Total | |
| Productive Labor Hours | 6.0000 | 15.0000 | 3.0000 | 3.0000 | 12.0000 | 0.00 | 15.0000 | 0.00 | 6.0000 | 60.0000 |
| GC Labor Hours | 0 | 0 | 0 | 0 | 0 | 4.00 | 0 | 0 | 0 | 4.00 |
| MOB Labor Hours | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 12.0000 | 0.00 | 12.0000 |
| Crew Labor Hours | 2.00 | 5.00 | 1.00 | 1.00 | 4.00 | 0 | 5.00 | 0 | 2.00 | 20.00 |
| Crew MOB Hours | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 4.00 | 0 | 4.00 |