Materials Sheet

NOTE: You have to reload this page before the materials sheet will update, hit F5.

Category Units Amount Cost To Buy List Total Purchased, Units Total Purchased, Dollar Amount
Fabric SQFT 48.00 $ 3.48 Fabric(48.00), 0 0 See Invoice List->
1-1/2" Rock TONS 13.00 $ 0.00 1-1/2" Local River Rock(12.00), 1-1/2" Local River Rock(1.00), 0 0 See Invoice List->
Boulders TONS 1.50 $ 0.00 Colorado Buff Boulders(1.50), 0 0 See Invoice List->
Wall TONS 8.00 $ 234.00 Wall Blocks(8.00), 0 0 See Invoice List->
Cap TONS 12.00 $ 102.00 Caps(12.00), 0 0 See Invoice List->
Topsoil TONS 2.00 $ 250.00 Top Soil(2.00), 0 0 See Invoice List->
Miscellaneous 1.00 $ 250.00 Miscellaneous(1.00), 0 0 See Invoice List->
Downspouts 1.00 $ 75.00 Downspouts(1.00), 0 0 See Invoice List->


Misc Items Needed:

Item Description Amount Needed Total Purchased, Units Total Purchased, Dollar Amount

French Drain

1.00 0 0 See Invoice List->




Fabric 1-1/2" Rock Boulders Wall Cap Topsoil Miscellaneous MOB Downspouts Total
Productive Labor Hours 3.0000 3.0000 6.0000 6.0000 6.0000 3.0000 6.0000 0.00 3.0000 36.0000
GC Labor Hours 0 0 0 0 0 0 0 0 0 0
MOB Labor Hours 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9.0000 0.00 9.0000
Crew Labor Hours 1.00 1.00 2.00 2.00 2.00 1.00 2.00 0 1.00 12.00
Crew MOB Hours 0 0 0 0 0 0 0 3.00 0 3.00