Materials Sheet

NOTE: You have to reload this page before the materials sheet will update, hit F5.

Category Units Amount Cost To Buy List Total Purchased, Units Total Purchased, Dollar Amount
Sod SQFT 1026.00 $ 459.55 Sod(513.00), Pallet(513.00), 0 0 See Invoice List->
Irrigation Zones ZONE 2.00 $ 644.00 # of zones(2.00), 0 0 See Invoice List->
Edging FT 108.00 $ 224.00 Edging(94.00), sticks(14.00), 0 0 See Invoice List->
Demo SQFT 513.00 $ 250.00 Demo Sod(513.00), 0 0 See Invoice List->
Tilling SQFT 513.00 $ 0.00 Roto-tilling SF(513.00), 0 0 See Invoice List->
Grading SQFT 513.00 $ 0.00 Finish Grading SF(513.00), 0 0 See Invoice List->
Compost TON 2.00 $ 100.00 Compost(2.00), 0 0 See Invoice List->
Concrete 306.00 $ 4089.00 Concrete,Grey Broom(303.00), Concrete,Stairs(3.00), 0 0 See Invoice List->
1 Gallon 3.00 $ 54.00 Perennial 1 gal(3.00), 0 0 See Invoice List->






Sod Irrigation Zones Edging Demo Tilling Grading Compost Concrete 1 Gallon MOB Total
Productive Labor Hours 6.0000 37.5000 6.0000 6.0000 3.0000 3.0000 3.0000 0.00 0.7200 0.00 65.2200
GC Labor Hours 0 0 0 0 0 0 0 7.00 0 0 7.00
MOB Labor Hours 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36.0000 36.0000
Crew Labor Hours 2.00 12.50 2.00 2.00 1.00 1.00 1.00 0 0.24 0 21.74
Crew MOB Hours 0 0 0 0 0 0 0 0 0 12.00 12.00
Edit - Landscaping_Software demo
mob
sod
tilling
grading
compost
sod
edging
edging
concrete
concrete
1 gallon
plants
mob
irrigation zones
mob