Customer: Old Town North The Summit HOA Management Company Bid #:3483 - install |
Click to jump to:
Auto-Reload
Bid Not Yet Awarded, See Bid Details
|
Privacy Fence |
Discount: 0.00 % | Customer can decline on the proposal: False |
| Item # | We Install | Error-CallTechSupport | ReuseMaterials |
L (Feet) |
W (Feet) |
H |
Enabled | Item | Difficulty | Amount | Units | Color | Dump Cost | UnitPrice | misc % | misc | tax |
Other+ Delivery |
Subtotal | Profit Margin Materials |
Labor Hours |
Labor Cost | GC Hours | Profit Margin Subs |
Profit Margin Labor |
total | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 |
|
(OLD)
Woodwork, Woodwork,6' cedar privacy
|
0.00 | 44.00 | % |
726.00
|
|
7986.00 | 1409.29 | 10.00 | 172.06 |
10542.35
|
||||||||||||||||||
| 2 |
|
(OLD)
Woodwork, Woodwork,Stain
|
0.00 | 5.00 | % |
82.50
|
|
907.50 | 160.15 | 2.00 | 34.41 |
1297.06
|
||||||||||||||||||
| 808.50 | 0.00 | 8893.50 | Privacy Fence | Scope Total: | 11839.41 |
Horizontal Fence |
Discount: 0.00 % | Customer can decline on the proposal: False |
| Item # | We Install | Error-CallTechSupport | ReuseMaterials |
L (Feet) |
W (Feet) |
H |
Enabled | Item | Difficulty | Amount | Units | Color | Dump Cost | UnitPrice | misc % | misc | tax |
Other+ Delivery |
Subtotal | Profit Margin Materials |
Labor Hours |
Labor Cost | GC Hours | Profit Margin Subs |
Profit Margin Labor |
total | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 |
|
(OLD)
Woodwork, Woodwork,6' cedar privacy
|
0.00 | 65.00 | % |
1072.50
|
|
11797.50 | 2081.91 | 14.00 | 240.88 |
15485.29
|
||||||||||||||||||
| 2 |
|
(OLD)
Woodwork, Woodwork,Stain
|
0.00 | 5.00 | % |
82.50
|
|
907.50 | 160.15 | 2.00 | 34.41 |
1297.06
|
||||||||||||||||||
| 1155.00 | 0.00 | 12705.00 | Horizontal Fence | Scope Total: | 16782.35 |
Concrete w/ Sails |
Discount: 0.00 % | Customer can decline on the proposal: False |
| Item # | We Install | Error-CallTechSupport | ReuseMaterials |
L (Feet) |
W (Feet) |
H |
Enabled | Item | Difficulty | Amount | Units | Color | Dump Cost | UnitPrice | misc % | misc | tax |
Other+ Delivery |
Subtotal | Profit Margin Materials |
Labor Hours |
Labor Cost | GC Hours | Profit Margin Subs |
Profit Margin Labor |
total | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 |
|
(OLD)
Concrete, Concrete,Grey Broom
|
0.00 | 13.00 | % |
790.40
|
|
8694.40 | 1534.31 | 11.00 | 189.26 |
11490.47
|
||||||||||||||||||
| 2 |
|
(OLD)
Concrete, Concrete,Boom Pump
|
0.00 | 600.00 | % |
|
|
|
||||||||||||||||||||||
| 3 |
|
(OLD)
Miscellaneous, Miscellaneous
|
0.00 | % |
|
1800.00 | 537.66 |
2337.66
|
||||||||||||||||||||||
| 4 |
|
(OLD)
MOB, MOB
|
0.00 | % |
|
|
4.00 | 900.00 | 268.83 |
1168.83
|
||||||||||||||||||||
| 790.40 | 0.00 | 8694.40 | Concrete w/ Sails | Scope Total: | 14996.96 |
Pavers w/ Sail |
Discount: 0.00 % | Customer can decline on the proposal: False |
| Item # | We Install | Error-CallTechSupport | ReuseMaterials |
L (Feet) |
W (Feet) |
H |
Enabled | Item | Difficulty | Amount | Units | Color | Dump Cost | UnitPrice | misc % | misc | tax |
Other+ Delivery |
Subtotal | Profit Margin Materials |
Labor Hours |
Labor Cost | GC Hours | Profit Margin Subs |
Profit Margin Labor |
total | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 |
|
Pavers, Paver Patio SQFT
|
0.00 | % |
|
|
|
|||||||||||||||||||||||
| 2 | --- |
Pavers, Pavers
|
0.00 | 7.00 | % |
425.60
|
300.00
|
4981.60 | 1488.01 | 61.00 | 13725.00 | 4099.68 |
24294.29
|
|||||||||||||||||
| 3 | --- |
Poli Sand, Poli-sand
|
0.00 | 60.00 | % |
54.00
|
|
594.00 | 177.43 |
771.43
|
||||||||||||||||||||
| 4 | --- |
Sand, Sand
|
0.00 | 43.00 | % |
12.90
|
150.00
|
291.90 | 87.19 |
379.09
|
||||||||||||||||||||
| 5 | --- |
Roadbase, Road base
|
0.00 | 35.00 | % |
80.50
|
300.00
|
1185.50 | 354.11 |
1539.61
|
||||||||||||||||||||
| 6 |
|
(OLD)
Miscellaneous, Miscellaneous
|
0.00 | % |
150.00
|
1650.00 | 492.86 | 1800.00 | 537.66 |
4480.52
|
||||||||||||||||||||
| 7 |
|
(OLD)
MOB, MOB
|
0.00 | % |
|
|
24.00 | 5400.00 | 1612.99 |
7012.99
|
||||||||||||||||||||
| 723.00 | 750.00 | 8703.00 | Pavers w/ Sail | Scope Total: | 38477.93 |
Sod & Irrigation |
Discount: 0.00 % | Customer can decline on the proposal: False |
| Item # | We Install | Error-CallTechSupport | ReuseMaterials |
L (Feet) |
W (Feet) |
H |
Enabled | Item | Difficulty | Amount | Units | Color | Dump Cost | UnitPrice | misc % | misc | tax |
Other+ Delivery |
Subtotal | Profit Margin Materials |
Labor Hours |
Labor Cost | GC Hours | Profit Margin Subs |
Profit Margin Labor |
total | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 |
|
(OLD)
Sod, Sod
|
SQFT | 0.00 | 0.35 | % |
107.14
|
358.14
|
1536.63 | 458.99 | 6.00 | 1350.00 | 403.25 |
3748.86
|
||||||||||||||||
| 2 | --- |
Tilling, Roto-tilling SF
|
SQFT | 0.00 | % |
|
|
2.00 | 450.00 | 134.42 |
584.42
|
|||||||||||||||||||
| 3 | --- |
(OLD)
Grading, Finish Grading SF
|
SQFT | 0.00 | % |
|
|
3.00 | 675.00 | 201.62 |
876.62
|
|||||||||||||||||||
| 4 | --- |
(OLD)
Compost, Compost
|
TON | 0.00 | 50.00 | % |
50.00
|
|
550.00 | 164.29 | 3.00 | 675.00 | 201.62 |
1590.91
|
||||||||||||||||
| 5 | --- |
Sod, Pallet
|
0.00 | 1.00 | % |
24.00
|
|
264.00 | 78.86 |
342.86
|
||||||||||||||||||||
| 6 |
|
(OLD)
Irrigation Zones, # of zones
|
ZONE | 0.00 | 322.00 | % |
322.00
|
|
3542.00 | 1058.00 | 62.50 | 14062.50 | 4200.49 |
22862.99
|
||||||||||||||||
| 7 |
|
Taps, Taps
|
ZONE | 0.00 | 1500.00 | % |
150.00
|
|
1650.00 | 492.86 |
2142.86
|
|||||||||||||||||||
| 8 |
|
Backflow, Backflow
|
ZONE | 0.00 | 150.00 | % |
15.00
|
|
165.00 | 49.29 |
214.29
|
|||||||||||||||||||
| 9 |
|
Drip, Drip
|
ZONE | 0.00 | 100.00 | % |
10.00
|
|
110.00 | 32.86 |
142.86
|
|||||||||||||||||||
| 10 |
|
(OLD)
MOB, MOB
|
0.00 | % |
|
|
26.00 | 5850.00 | 1747.40 |
7597.40
|
||||||||||||||||||||
| 678.14 | 358.14 | 7817.63 | Sod & Irrigation | Scope Total: | 40104.07 |
Planting Beds |
Discount: 0.00 % | Customer can decline on the proposal: False |
| Item # | We Install | Error-CallTechSupport | ReuseMaterials |
L (Feet) |
W (Feet) |
H |
Enabled | Item | Difficulty | Amount | Units | Color | Dump Cost | UnitPrice | misc % | misc | tax |
Other+ Delivery |
Subtotal | Profit Margin Materials |
Labor Hours |
Labor Cost | GC Hours | Profit Margin Subs |
Profit Margin Labor |
total | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 |
|
|
|
(Inches) |
Mulch, Shredded Redwood Mulch
|
SQ YD | 0.00 | 90.00 | % |
171.00
|
300.00
|
2181.00 | 651.47 | 4.00 | 900.00 | 268.83 |
4001.30
|
|||||||||||||
| 2 |
|
1 Gallon, Perennial 1 gal
|
0.00 | 18.00 | % |
37.80
|
|
415.80 | 124.20 | 1.68 | 378.00 | 112.91 |
1030.91
|
|||||||||||||||||
| 3 |
|
Plants, Tree/Plant Delivery Cost
|
0.00 | % |
|
275.00
|
275.00 | 82.14 |
357.14
|
|||||||||||||||||||||
| 4 |
|
5 Gallon Shrub, Shrub 5 gal
|
0.00 | 45.00 | % |
90.00
|
|
990.00 | 295.71 | 3.20 | 720.00 | 215.06 |
2220.77
|
|||||||||||||||||
| 5 |
|
Edging, Edging
|
FT | 0.00 | % |
|
|
2.00 | 450.00 | 134.42 |
584.42
|
|||||||||||||||||||
| 6 | --- |
Edging, sticks
|
0.00 | 16.00 | % |
35.20
|
|
387.20 | 115.66 |
502.86
|
||||||||||||||||||||
| 7 |
|
Boulders, Aspen Boulders
|
Ton | 0.00 | 170.00 | % |
102.00
|
150.00
|
1272.00 | 379.95 | 6.00 | 1350.00 | 403.25 |
3405.20
|
||||||||||||||||
| 8 |
|
Boulder, Boulder Delivery Cost
|
0.00 | % |
|
150.00
|
150.00 | 44.81 |
194.81
|
|||||||||||||||||||||
| 9 |
|
2" Tree, Tree 2"
|
0.00 | 425.00 | % |
382.50
|
|
4207.50 | 1256.79 | 6.75 | 1518.75 | 453.65 |
7436.69
|
|||||||||||||||||
| 10 |
|
(OLD)
Fabric, Fabric
|
SQFT | 0.00 | 87.00 | % |
13.66
|
|
150.25 | 44.88 | 2.00 | 450.00 | 134.42 |
779.55
|
||||||||||||||||
| 11 |
|
(OLD)
MOB, MOB
|
0.00 | % |
|
|
10.00 | 2250.00 | 672.08 |
2922.08
|
||||||||||||||||||||
| 832.16 | 875.00 | 10028.75 | Planting Beds | Scope Total: | 23435.73 |