Customer: Jeff Wohlfarth Bid #:17819 - install

Click to jump to:
+ Quick Add New Scope/Area
Auto-Reload
Bid Not Yet Awarded, See Bid Details

Pavers

PopOut->

Edit->

Discount: 0.00 % Customer can decline on the proposal: False
Item # We Install Error-CallTechSupport ReuseMaterials L
(Feet)
W
(Feet)
H
Enabled Item Difficulty Amount Units Color Dump Cost UnitPrice misc % misc tax Other+
Delivery
Subtotal Profit
Margin
Materials
Labor
Hours
Labor Cost GC Hours Profit Margin Subs Profit
Margin
Labor
total
1
PopOut
Pavers, Paver Patio SQFT
0 %
2 ---
Pavers, Pavers
0.00 7.00 %
189.00
150
2229.00 247.67 25 5625.00 1680.19
9781.86
3 ---
Poli Sand, Poli-sand
0.00 60.00 %
24.00
264.00 29.33
293.33
4 ---
Sand, Sand
0 43.00 %
8.60
150
244.60 27.18
271.78
5 ---
Roadbase, Road base
0 35.00 %
38.50
150
573.50 63.72
637.22
7
260.10 450.00 3311.10 Pavers Scope Total:
13906.2700000000000000
 

Irrigation

PopOut->

Edit->

Discount: 0.00 % Customer can decline on the proposal: False
Item # We Install Error-CallTechSupport ReuseMaterials L
(Feet)
W
(Feet)
H
Enabled Item Difficulty Amount Units Color Dump Cost UnitPrice misc % misc tax Other+
Delivery
Subtotal Profit
Margin
Materials
Labor
Hours
Labor Cost GC Hours Profit Margin Subs Profit
Margin
Labor
total
1
PopOut
Taps, Taps
ZONE 0 1500.00 %
150.00
1650.00 183.33
1833.33
2
PopOut
Backflow, Backflow
ZONE 0 150.00 %
15.00
165.00 18.33
183.33
3
PopOut
(OLD)
Irrigation Zones, # of zones
ZONE 0 322.00 %
32.20
354.20 39.36 2.50 562.50 168.02
1124.08
4
PopOut
(OLD)
MOB, MOB
0 %
2 450.00 134.42
584.42
5
197.20 0.00 2169.20 Irrigation Scope Total:
3725.1600000000000000
 

Planting Beds

PopOut->

Edit->

Discount: 0.00 % Customer can decline on the proposal: False
Item # We Install Error-CallTechSupport ReuseMaterials L
(Feet)
W
(Feet)
H
Enabled Item Difficulty Amount Units Color Dump Cost UnitPrice misc % misc tax Other+
Delivery
Subtotal Profit
Margin
Materials
Labor
Hours
Labor Cost GC Hours Profit Margin Subs Profit
Margin
Labor
total
1
PopOut


(Inches)
3/8" Pea Gravel, 3/8" pea gravel
TONS 0 60.00 %
228.00
2508.00 278.67 6 1350.00 403.25
4539.92
2
PopOut


(Inches)
Topsoil, Top Soil
TONS 0 50.00 %
210.00
450
2760.00 306.67 11 2475.00 739.29
6280.96
3
PopOut
Boulders, Granite Boulders
Ton 0.00 184.05 %
128.84
150
1567.18 174.13 5 1125.00 336.04
3202.36
4
PopOut
Boulder, Boulder Delivery Cost
0 %
150.0
150.00 16.67
166.67
5
PopOut
(OLD)
Fabric, Fabric
SQFT 0 87.00 %
27.55
303.05 33.67 2 450.00 134.42
921.14
6
PopOut
(OLD)
MOB, MOB
0 %
8 1800.00 537.66
2337.66
7
594.38 750.00 7288.24 Planting Beds Scope Total:
17448.705000000000000000
 

Demo

PopOut->

Edit->

Discount: 0.00 % Customer can decline on the proposal: False
Item # We Install Error-CallTechSupport ReuseMaterials L
(Feet)
W
(Feet)
H
Enabled Item Difficulty Amount Units Color Dump Cost UnitPrice misc % misc tax Other+
Delivery
Subtotal Profit
Margin
Materials
Labor
Hours
Labor Cost GC Hours Profit Margin Subs Profit
Margin
Labor
total
1
PopOut
Demo, Demo Sod
SQFT 400.00 %
40.00
600
1040.00 115.56 3 675.00 201.62
2032.18
2
PopOut
Demo, Demo Rock
SQFT 200.00 %
20.00
300
520.00 57.78 2 450.00 134.42
1162.20
3
PopOut
(OLD)
Miscellaneous, Miscellaneous


0 %
200.00
2200.00 244.44 1800.00 537.66
4782.10
4
PopOut
(OLD)
Miscellaneous, Miscellaneous


0 %
500.00 55.56 900.00 268.83
1724.39
5
PopOut
(OLD)
MOB, MOB
0 %
6 1350.00 403.25
1753.25
6
260.00 1400.00 4260.00 Demo Scope Total:
11454.1200000000000000
 
 

This bid Created By: at 1/1/0001 12:00 AM


This bid last edited by: at 12/15/2025 10:50 PM

 
Edit - Landscaping_Software
Grand Total: $ 46534.255000000000000000