Embedded edit pop-up window for: Area: Sidewalk Parent Item: Paver Sidewalk SQFT

Use CTRL and + or CTRL and - on your keyboard to zoom in and out to make the text bigger. To reset it, hold CTRL and press 0.

Sidewalk

Pavers

PopOut->

Edit->

Discount: 0.00 % Customer can decline on the proposal: False
Item # We Install Error-CallTechSupport ReuseMaterials L
(Feet)
W
(Feet)
H
Enabled Item Difficulty Amount Units Color Dump Cost UnitPrice misc % misc tax Other+
Delivery
Subtotal Profit
Margin
Materials
Labor
Hours
Labor Cost GC Hours Profit Margin Subs Profit
Margin
Labor
total
1 (OLD)
Pavers, Paver Sidewalk SQFT
0.00 %
2 ---
Pavers, Pavers
0.00 7.00 %
226.80
150.00
2644.80 790.01 33.00 7425.00 2217.86
13077.67
3 ---
Poli Sand, Poli-sand
0.00 60.00 %
30.00
150.00
480.00 143.38
623.38
4 ---
Sand, Sand
0.00 43.00 %
8.60
150.00
244.60 73.06
317.66
5 ---
Roadbase, Road base
0.00 35.00 %
45.50
150.00
650.50 194.31
844.81
6

(Feet)
Wall Calculation, Block Retaining Wall
0.00 %
7 ---
Wall, Wall Blocks
TONS 0.00 10.50 %
63.00
150.00
843.00 251.81 11.00 2475.00 739.29
4309.10
8 ---
Cap, Caps
TONS 0.00 8.50 %
76.50
841.50 251.36 11.00 2475.00 739.29
4307.15
9 ---
Roadbase, Road base
TONS 0.00 35.00 %
0.10
150.00
151.10 45.13
230.23
10 ---
1-1/2" Rock, 1-1/2" Local River Rock
0.00 60.00 %
11
Miscellaneous, Miscellaneous


0.00 %
25.00
275.00 82.14 675.00 201.62
1233.76
13
MOB, MOB
0.00 %
20.00 4500.00 1344.16
5844.16
14
490.50 900.00 6295.50 Sidewalk Scope Total:
31294.42
 

This bid Created By: at 1/1/0001 12:00 AM


This bid last edited by: at 12/15/2025 8:58 AM

 
Edit - Landscaping_Software
Grand Total: $ 31294.42