Render Billing as PDF, Schedule of Values
| BB Court demo | Picnic table | Temp Fencing | Lighting | ||
| Total | 79748 | 12254 | 12532 | 12176 | 42786 |
| Materials | 50903.92 | 2310.00 | 7398.92 | 8250.00 | 32945.00 |
| Subcontractors | 0 | 0 | 0 | 0 | 0 |
| Other/Delivery | 2400.00 | 2400.00 | 0.00 | 0.00 | 0.00 |
| Equipment | |||||
| Labor | 6750.00 | 4050.00 | 1800.00 | 900.00 | 0.00 |
| MOB | 1350.00 | 675.00 | 450.00 | 225.00 | 0.00 |
| Taxes | |||||
| Profit | 18344.08 | 2819.00 | 2883.08 | 2801.00 | 9841.00 |
| Project Scope | Contract | Completed | % Complete | + Add Day | |
|---|---|---|---|---|---|
| BB Court demo | 12254.00 | 0 % | 0.00 | ||
| Picnic table | 12532.00 | 0 % | 0.00 | ||
| Temp Fencing | 12176.00 | 0 % | 0.00 | ||
| Lighting | 42786.00 | 0 % | 0.00 | ||
|
|||||
Total Project Completion: 0 %
Helper: 50% down is: 39872.68