Render Billing as PDF, Schedule of Values
| Ruberg Landscape renovation | fabric and rock | ||
| Total | 7857 | 5968 | 1889 |
| Materials | 1061.92 | 770.00 | 291.92 |
| Subcontractors | 0 | 0 | 0 |
| Other/Delivery | 600.00 | 450.00 | 150.00 |
| Equipment | |||
| Labor | 3375.00 | 2700.00 | 675.00 |
| MOB | 1012.50 | 675.00 | 337.50 |
| Taxes | |||
| Profit | 1807.59 | 1373.00 | 434.59 |
| Project Scope | Contract | Completed | % Complete | + Add Day | |
|---|---|---|---|---|---|
| Ruberg Landscape renovation | 5968.00 | 0 % | 0.00 | ||
| fabric and rock | 1889.00 | 0 % | 0.00 | ||
|
|||||
Total Project Completion: 0 %
Helper: 50% down is: 3928.19