Render Billing as PDF, Schedule of Values

Sheet Billing

Demo Planting Bed Sod Retaining Wall Backyard Plants Front Yard Concrete
Total 50916 9247 9888 9144 8720 2211 4645 7061
Materials 10736.94 1870.00 2588.38 2902.85 2187.90 337.70 850.11 0
Subcontractors 4322.00 0 0 0 0 0 0 4322.00
Other/Delivery 3337.85 750.00 750.00 537.85 450.00 275.00 575.00 0.00
Equipment
Labor 17197.50 3825.00 3600.00 3150.00 3375.00 864.00 1701.00 682.50
MOB 3150.00 675.00 675.00 450.00 675.00 225.00 450.00 0
Taxes
Profit 11705.53 2127.00 2274.63 2103.31 1998.10 509.30 1068.89 1624.30





Trackable Billing

Billing

Project Scope Contract Completed % Complete + Add Day
Demo 9247.00 0 % 0.00
Planting Bed 9888.00 0 % 0.00
Sod 9144.00 0 % 0.00
Retaining Wall 8720.00 0 % 0.00
Backyard Plants 2211.00 0 % 0.00
Front Yard 4645.00 0 % 0.00
Concrete 7061.00 0 % 0.00

    

Total Project Completion: 0 %

Helper: 50% down is: 25456.28