Render Billing as PDF, Schedule of Values
| landscape reno | ||
| Total | 3761 | 3761 |
| Materials | 533.48 | 533.48 |
| Subcontractors | 0 | 0 |
| Other/Delivery | 600.00 | 600.00 |
| Equipment | ||
| Labor | 1175.00 | 1175.00 |
| MOB | 587.50 | 587.50 |
| Taxes | ||
| Profit | 865.02 | 865.02 |
| Project Scope | Contract | Completed | % Complete | + Add Day | |
|---|---|---|---|---|---|
| landscape reno | 3761.00 | 0 % | 0.00 | ||
|
|||||
Total Project Completion: 0 %
Helper: 50% down is: 1880.495