Render Billing as PDF, Schedule of Values

Sheet Billing, Holiday Lighting, Install

C9 LED Roofline (Bulbs Included), 862.21
Holiday Lighting Minimum 150 and 8 Hour Labor Reconciliation, 132.73
MOB, 278.40
50 Foot Towable Boom, 506.75
Holiday Lighting
Total 1780.09 1780.09
Materials 843.13 843.13
Subcontractors 0 0
Other/Delivery 0.00 0.00
Equipment
Labor 643.80 643.80
Taxes
Profit 134.14 134.14

Sheet Billing, Holiday Lighting, Takedown

Takedown, 156.60
Holiday Lighting
Total 156.60 156.60
Materials 0.00 0.00
Subcontractors 0 0
Other/Delivery 0.00 0.00
Equipment
Labor 156.60 156.60
Taxes
Profit 0.00 0.00

Trackable Billing

Billing

Project Scope Contract Completed % Complete + Add Day
Holiday Lighting 1937.00 0 % 0.00

    

Total Project Completion: 0 %

Helper: 50% down is: 968.345

Edit - Landscaping_Software