Render Billing as PDF, Schedule of Values

Sheet Billing, Holiday Lighting, Install

Miscellaneous, Holiday Lighting, 1797.95
Holiday Lighting Minimum 150 and 8 Hour Labor Reconciliation, 87.50
MOB, 656.00
Swagging - Canopy Lights - 36", 516.77
72" LED Wreath, 521.82
Swagging - Canopy Lights - 36", 2309.90
Holiday Lighting Minimum 150 and 8 Hour Labor Reconciliation, 93.28
2025 Reinstall Holiday lights New Trees
Total 5983.22 3580.04 2403.18
Materials 2565.16 1337.50 1227.66
Subcontractors 0 0 0
Other/Delivery 0.00 0.00 0.00
Equipment
Labor 2372.85 1694.59 678.26
Taxes
Profit 776.19 335.65 440.54

Sheet Billing, Holiday Lighting, Takedown

Installation and Removal - Swagging Canopy Lights takedown, 202.50
Takedown, 223.51
Installation and Removal - Swagging Canopy Lights takedown, 265.82
2025 Reinstall Holiday lights New Trees
Total 691.83 426.01 265.82
Materials 0.00 0.00 0.00
Subcontractors 0 0 0
Other/Delivery 0.00 0.00 0.00
Equipment
Labor 691.83 426.01 265.82
Taxes
Profit 0.00 0.00 0.00

Trackable Billing

Billing

Project Scope Contract Completed % Complete + Add Day
2025 Reinstall Holiday lights 4007.00 0 % 0.00
New Trees 2669.00 0 % 0.00

    

Total Project Completion: 0 %

Helper: 50% down is: 3337.525

Edit - Landscaping_Software