Render Billing as PDF, Schedule of Values

Sheet Billing

Old re-used material in use, billing sheet will need to be computed manually.

Front Back Yard
Total 28457 12514 15943
Materials 5746.44 3469.99 2276.45
Subcontractors 0 0 0
Other/Delivery 2650.00 1025.00 1625.00
Equipment
Labor 10234.13 4168.13 6066.00
MOB 4050.00 1800.00 2250.00
Taxes
Profit 6775.75 3126.20 3649.55





Trackable Billing

Billing

Project Scope Contract Completed % Complete + Add Day
Front 12514.00 0 % 0.00
Back Yard 15943.00 0 % 0.00

    

Total Project Completion: 0 %

Helper: 50% down is: 14227.995

Edit - Landscaping_Software