Render Billing as PDF, Schedule of Values

Sheet Billing, Holiday Lighting, Install

Raw Install Labor, 458.90
MOB, 275.34
2025 Holiday Lighting
Total 734.24 734.24
Materials 0.00 0.00
Subcontractors 0 0
Other/Delivery 0.00 0.00
Equipment
Labor 536.00 536.00
Taxes
Profit 198.24 198.24

Sheet Billing, Holiday Lighting, Takedown

Raw Takedown Labor, 183.56
2025 Holiday Lighting
Total 183.56 183.56
Materials 0.00 0.00
Subcontractors 0 0
Other/Delivery 0.00 0.00
Equipment
Labor 134.00 134.00
Taxes
Profit 49.56 49.56

Trackable Billing

Billing

Project Scope Contract Completed % Complete + Add Day
2025 Holiday Lighting 918.00 0 % 0.00

    

Total Project Completion: 0 %

Helper: 50% down is: 458.9