Render Billing as PDF, Schedule of Values

Sheet Billing, Holiday Lighting, Install

Raw Install Labor, 2624.00
MOB, 1312.00
50 Foot Towable Boom, 730.00
2025 Holiday Lighting
Total 4666.00 4666.00
Materials 0.00 0.00
Subcontractors 0 0
Other/Delivery 0.00 0.00
Equipment
Labor 4666.00 4666.00
Taxes
Profit 0.00 0.00

Sheet Billing, Holiday Lighting, Takedown

Raw Takedown Labor, 1230.00
2025 Holiday Lighting
Total 1230.00 1230.00
Materials 0.00 0.00
Subcontractors 0 0
Other/Delivery 0.00 0.00
Equipment
Labor 1230.00 1230.00
Taxes
Profit 0.00 0.00

Trackable Billing

Billing

Project Scope Contract Completed % Complete + Add Day
2025 Holiday Lighting 5896.00 0 % 0.00

    

Total Project Completion: 0 %

Helper: 50% down is: 2948.0