Render Billing as PDF, Schedule of Values

Sheet Billing, Holiday Lighting, Install

Raw Install Labor, 246.00
MOB, 164.00
2025 Holiday Lighting
Total 410.00 410.00
Materials 0.00 0.00
Subcontractors 0 0
Other/Delivery 0.00 0.00
Equipment
Labor 410.00 410.00
Taxes
Profit 0.00 0.00

Sheet Billing, Holiday Lighting, Takedown

Raw Takedown Labor, 246.00
2025 Holiday Lighting
Total 246.00 246.00
Materials 0.00 0.00
Subcontractors 0 0
Other/Delivery 0.00 0.00
Equipment
Labor 246.00 246.00
Taxes
Profit 0.00 0.00

Trackable Billing

Billing

Project Scope Contract Completed % Complete + Add Day
2025 Holiday Lighting 656.00 0 % 0.00

    

Total Project Completion: 0 %

Helper: 50% down is: 328.0

Edit - Landscaping_Software